New York City requires owners of taller buildings to have the exterior walls examined on a five-year cycle and to file the results with the Department of Buildings. The program is the Facade Inspection and Safety Program, set out in 1 RCNY 103-04. Many owners still call it Local Law 11. The name on the FISP filing is FISP.
Property managers are usually the people who notice the date, hire the inspector, and explain the result to a board. This note is for that conversation. It is general. It is not a legal opinion, and it is not a determination of what any one building must file.
Who has to file
In general, buildings greater than six stories are in the program. A building with six stories above grade plus a cellar can also be covered when more than half the cellar height is above the adjacent ground at any exterior wall. Wall sections that sit very close to a neighbor are treated differently under the rule. A Qualified Exterior Wall Inspector, a professional engineer or registered architect who meets the Department's experience rules, makes the technical call. Confirm the building in DOB NOW: Safety before you build a calendar around a guess.
When Cycle 10 is due
Cycle 10 opened on February 21, 2025 and runs through February 20, 2030. There is not one citywide due date. The Department splits the cycle by the last digit of the tax block number. The block controls the window, not the street address and not the borough.
Sub-cycle 10A covers blocks ending in 4, 5, 6, or 9. The filing window runs from February 21, 2025 to February 21, 2027.
Sub-cycle 10B covers blocks ending in 0, 7, or 8. The window runs from February 21, 2026 to February 21, 2028.
Sub-cycle 10C covers blocks ending in 1, 2, or 3. The window runs from February 21, 2027 to February 21, 2029.
These dates follow the Department's Cycle 10 diagram and 1 RCNY 103-04. Confirm the block, and the current status, in DOB NOW: Safety. A published list of subject buildings is a help. It does not replace the owner's duty to confirm.
Safe, SWARMP, and an Unsafe facade
The report classifies the facade as Safe, SWARMP, or Unsafe.
Safe means the inspector did not find conditions that the rule requires to be repaired before the next cycle. It is not a promise that nothing will ever crack. It is a classification of what was observed.
SWARMP means safe with a repair and maintenance program. The wall is considered safe at the time of the report, and named conditions must be repaired so they do not become unsafe. The owner needs a scope, a contractor, and a path to an amended filing. Leaving a SWARMP item in place until the next cycle is how buildings pick up penalties and, later, an Unsafe status.
An Unsafe facade means a condition hazardous to people or property. Public protection, often a sidewalk shed, a fence, or netting, goes up immediately. Repairs follow, and an amended report has to document that the condition was corrected. The shed is not the repair. Owners who treat the shed as the project live with a dark sidewalk and a standing cost.
What to have in hand before the window
Know the block number and the sub-cycle. Guessing from the street address is a common way to miss the window.
Retain the inspector early enough to probe, not only to look from across the street. Close-up examination is the point of the program.
Read the prior cycle report before you bid repairs. The new report will compare conditions with what was filed last time. A condition that was reported and not repaired is the item a board should expect to discuss.
Separate the examination from the repair contract. The firm that classifies the wall should not be the only voice on what the repair costs. Bid the work on a clear scope, level the numbers, and decide what must happen in this cycle.
Plan sidewalk shed removal before the shed goes up. Ask what repair sequence gets it down. A shed exit is part of the project, not a hope you add in month fourteen.
Put the filing date, the current status, and the open DOB violations on one page. FISP is one compliance item. Local Law 126 garages and other open violations often sit on the same building and compete for the same capital budget. A short briefing on Local Law 126 belongs in the same owner packet when the building has a garage.
Where a construction manager fits
An owner's representative does not replace the Qualified Exterior Wall Inspector and does not seal the report. The work that hurts owners is the work around the report: comparing repair bids, controlling change orders once probes are open, keeping the schedule honest, and pushing the project to an amended Safe filing or a completed SWARMP program.
Mewad provides that management for property management companies. Engineering design, sealing of documents, and means and methods stay with the licensed professionals who hold those duties. Rules and penalty amounts change. Confirm the current requirement with the Department of Buildings and with the inspector retained for the building.